OUR PROCESS
Supply & Installation Options

At ASAP Cabinetry, we understand that every client has a different level of experience, time availability, and involvement preference. That’s why we offer flexible solutions to suit your needs.

You can choose from:

  • A complete supply and installation service handled by our experienced team

  • Pre-assembled cabinetry designed for straightforward on-site installation

  • Flatpack options for clients who prefer a full DIY approach

Whichever option you select, we’ll tailor the process to ensure it works smoothly for your project.

DESIGN TIMELINE

01

Get in touch with us to arrange a free design consultation, where we discuss your ideas, space, and requirements.

02

Detailed proposal of costing presented

03

Formal site measure within 48 hours

04

3 weeks later start installation process

05

Review the design and material selection

06

Sign off on proposal and 50% deposit payment

07

Final working drawings presented for approval

WHAT TO EXPECT DURING INSTALLATION

ASAP Logo

DAY 1

 Site Preparation

Existing plumbing, gas, and electrical connections are safely disconnected

Removal of old cabinetry and splashbacks

If no additional structural work is required
*Any re-tiling, relocation of power points, or plumbing adjustments must be completed before new cabinets are installed.

ASAP Logo

DAY 2

Cabinet Installation

New cabinets are delivered and installed on site

Alignment and positioning are checked to ensure accuracy and functionality

 
ASAP Logo

DAY 3

Benchtop Measuring

In the afternoon, the stone mason measures for the benchtop

Allow approximately 5 – 7 working days for stone fabrication

ASAP Logo

DAY 8

Benchtop Installation

Benchtop is delivered and professionally installed

ASAP Logo

DAY 9

Splashback Installation

  • Tiled splashback is installed

If a glass splashback is selected, measurements are taken after the benchtop is installed. Please allow up to 3 weeks for manufacture (the kitchen remains usable during this time).
If a stone splashback is selected, allow approximately 5 working days.

ASAP Logo

DAY 10

Final Fit-Off

  • Final plumbing and electrical fixtures are installed

  • Project completion and final checks

Your kitchen is now complete — ready to be enjoyed for years to come.